Progress report on Go!Durban project

19 November 2015 by Alan

Significant progress has been made with the Integrated Rapid Public Transport Network (IRPTN), Go!Durban project which is set to revolutionise the public transport system in eThekwini.

Details of progress made were announced at a media briefing at the Moses Mabhida Stadium today, 19 November 2015 to keep local media up to date on the project.

Construction work is well underway at two transport corridors namely C3, linking Bridge City, KwaMashu to Pinetown and C9 running between Umhlanga and KwaMashu.

At the C3 corridor, bulk earthworks and excavations have been completed through the majority of the route with good progress made on bridges. Preparatory civil works for stations have commenced with 1.3 kilometres of right of way already completed.

Other significant strides made include the signing of a memorandum of agreement (MOA) with the taxi industry in February last year. A MOA was also agreed upon with bus operators and is pending a signing ceremony.

Taxi industry technical advisors were appointed in October last year with the appointment of bus operators’ technical advisors being finalised.

The establishment of negotiations structures in line with the MOA has been completed. The programme of action budget is also being finalised.

A survey for revenue and skills audit is also being finalised. This is to ensure that no jobs are lost and those employed by affected operators are reskilled and can work in the new transport model.

Head of eThekwini Transport Authority Thami Manyathi said while the project is expected to take 15 years to complete, it will leave a lasting legacy in the City with a safe, improved public transport model.

He said almost 85 percent of residents will be in close proximity to some form of the transport system.

“We have designed the complete transport solution for the City, we are now mapping out the implementation. Operational readiness will be our key focus in 2016 with the first corridor (C3) opening in 2017,” Manyathi said.

He said other infrastructure required for the C3 Corridor include transfer stations, a terminal station, a depot and transport management centre.

“Safety is very important for people who leave their cars at home and opt to use public transport,” he said.

He acknowledged that there have been some challenges thus far including mini bus taxi operators stopping work demanding a stake in the construction and service delivery protests, both which were dealt with.

Regarding concerns about the effect Go!Durban would have on the taxi industry, Deputy Head of ETA Mlungisi Wosiyala said not all the 112 taxi associations in eThekwini would be affected by the IRPTN.

“This will be an integrated service with various modes. Negotiation structures are being finalised and negotiations are expected to start in March 2016. Some operators may have to upgrade their skills. We are doing a skills audit to determine this. We will try ensure there are no job losses,” he said.

He said affected operators can opt for a payout for withdrawal of their operating licence or they can form companies that will be contracted to provide the services on affected routes. In return for the bus operating contracts, the affected operators will be required to withdraw their vehicles on that particularly affected route.

EThekwini Mayor James Nxumalo said it was important to keep the public updated on the project.

Nxumalo said he was on site in Pinetown before the media briefing and was impressed with the work done thus far.

“The project is moving along. However, we need to maximise employment opportunities at both sites for the youth. This is a legacy project for the City,” he said.

Category: GovernmentTag: Bus, Go Durban, IRPTN

About Alan

The one with a “My Complex” – incurable but fun. Grumpy, Cynical, Wise and Idiotic. I can also be found HERE.

Previous Post:Durban Image: knysna, capetown, onderstepoort, durban 292
Next Post:Scrap metal battle sends cops to hospital

Building Automation, Prepaid Meters and Home Automation Products.

Stratlec offers everything you need to MEASURE, MANAGE and SAVE Electricity

Shop Online

MyZA News

  • Currie Cup Bulletin #28 – Champions Edition
  • Eskom Must Come Clean on the Real Cost of Medupi and Kusile
  • Springboks beat All Blacks again to clinch tour series – SABC News – Breaking news, special reports, world, business, sport coverage of all South African current events. Africa’s news leader. | SA News
  • Golden Boks add to legacy | SA News
  • FIFA and CAF congratulate Dr Jordaan after successful SAFA Elective Congress – South African Football Association

MyPR News

  • Boxer Super Run Durban Boasts a “Fast, Flat and Scenic” Route in 2026
  • Mangaung Ready to Experience Road Running at Its Best at the Inaugural Absa RUN YOUR CITY MANGAUNG 10K
  • Top Click Turns AI Answer Visibility Into a Tracked Metric
  • Pawn Your Car and Still Drive It Open Six Days a Week
  • Mann Made Media Backs Year-End Events With Animation

Cape Town News

  • Double Surf-ski Paddlers Rescued
  • Agriculture Sector Urged to Prepare Adequately for Impact of ENSO
  • Kloof Nek Road Compulsory Stop
  • A Pivotal Arrest
  • Rise Student Living: What Students Need to Apply for 2027

NMB News

  • Body Discovered in Kwanoxolo, Bethelsdorp
  • Baby Abandoned in Spondo Road – SAPS Seek Mother
  • SAPS Warn Gqeberha Retirement Villages
  • E-bicycles Valued at R500 000 Recovered in Wells Estate
  • Dear Babalwa – Here is Your Tweetable SOMA Report

Copyright © 2026 · All Rights Reserved · Powered by Straton Solar