Project to Restore Durban Dry Dock in Full Swing

Project to Restore Durban Dry Dock in Full Swing:

The Prince Edward Graving Dock’s inner caisson is presently undergoing repair.

The Prince Edward Graving Dock’s inner caisson is presently undergoing repair.

The rehabilitation of the inner caisson, which divides the Port of Durban’s Prince Edward Graving Dock into two compartments, enabling two smaller vessels to be docked simultaneously, is in full swing.

It is among 11 large-scale projects earmarked for the Durban Dry Dock complex, of which the R48 million refurbishment of the dry dock’s 35-metre-long, 900ton outer caisson which closes off the dry dock from the rest of the harbour, was the first to be completed in 2016.

“The R 61 500 700 project to repair the inner caisson and upgrade the drive system has been undertaken to ensure the safety of the dry dock and the sustainability of the ship repair business in Durban,” said Dumisani Mkhize, Deputy Port Engineer at the Port of Durban, who is managing the project.

Erwin Skeepers, Business Unit Manager: Ship Repair and Workshops in the Port of Durban, added: “Rehabilitation of the inner caisson will improve the operational efficiency, reinstate the dry dock to its full capacity and improve operational safety. It will equip ship repairers who use our facility to be more competitive, helping to attract more business to South Africa.”

The rehabilitation follows extensive technical studies which identified parts of the caisson that had aged and deteriorated and were in need of attention. Various options were explored with professional inputs and ultimately it was decided to repair the inner caisson to the original design.

The rehabilitation includes major structural design improvements on re-built decks and compartments, which are being built in a controlled environment in an off-site engineering workshop. These will be pre-trial fitted before being sent to site, greatly improving fabrication quality and ease of fitment on site. Design and fabrication of the new steel sections has already been completed.

“The caisson has been taken apart at C and D deck levels and the A and B deck steel structures have been cut up for scrap. The next big milestone will be bringing new sections of C and D decks for installation on top of the rehabilitated DE section,” said Mkhize.

The project, which is being carried out by two Durban-based companies, Lodemann (Managing Contractor) and Channel Construction (Design and Build) – both of which were appointed in May 2018 – is expected to be completed by November 2019.

The work schedule is being managed in consultation with the Ship Repair Industry to promote a “win-win” situation where ship repair work in the dock may be reasonably sustained during the project.

The rehabilitation project falls within TNPA’s contribution to Operation Phakisa – the government initiative to unlock the oceans economy by investing in infra-structure, skills and capacity building, in order to grow the market and in so doing, create much needed jobs.

Job creation in the marine sector has a strong multiplier effect, with an estimated 5 indirect jobs created for every direct job. This particular contract has created direct jobs for 29 skilled employees, including 7 youth, and 9 semi-skilled jobs, including 3 youth.

CLICK HERE to submit your press release to MyPR.co.za.

Click HERE to submit your Durban / Kwazulu-Natal Press Release.

Why don’t you stay here on your next visit to Durban?

Quayside on Timeball

Click HERE for Quayside on Timeball rates and booking info. Quayside on Timeball is a luxurious, modern apartment situated near the waterside of Durban Point. The self-catering apartment can comfortably sleep six people and offers all the luxuries from home. The open-plan design features a clean kitchen with ample cupboard space and modern cooking facilities. The large counter top also serves as a dining table and overlooks the lounge area with a large comfortable sofa and a wall-mounted flat screen TV with DStv. The lounge and dining area has large glass doors leading out onto a balcony with a small patio set, barbecue facilities, and views across the canal. The ground level features one of the bedrooms. The second and third bedrooms are located in the upstairs loft area and these rooms have large glass walls looking over the lounge and kitchen. The apartment features air-conditioning throughout and there is also a security alarm system in place for guests' peace of … [Book here...]


Click here to showcase your Durban accommodation for free.
About Alan

The one with a "My Complex" - incurable but fun. Grumpy, Cynical, Wise and Idiotic. I can also be found HERE.